Which of the following is not a concept associated with CPM?
A) normal time
B) probability
C) normal cost
D) crash cost
Correct Answer:
Verified
Q34: Given an activity's optimistic, most likely, and
Q35: Budgets are computed using only ES times.
Q36: PERT
A)assumes that we do not know ahead
Q37: For projects that have a daily fixed
Q38: Slack time in a network is the
A)amount
Q40: In a PERT network, the earliest (activity)start
Q41: Table 11-1
The following represents a project with
Q42: Given an activity's optimistic, most likely, and
Q43: Given the following small project, the critical
Q44: Table 11-2
The following represents a project with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents