Slack time in a network is the
A) amount of time that an activity would take assuming very unfavorable conditions.
B) shortest amount of time that could be required to complete the activity.
C) amount of time that you would expect it would take to complete the activity.
D) amount of time that an activity can be delayed without delaying the entire project.
Correct Answer:
Verified
Q33: The activity difference is the actual duration
Q34: Given an activity's optimistic, most likely, and
Q35: Budgets are computed using only ES times.
Q36: PERT
A)assumes that we do not know ahead
Q37: For projects that have a daily fixed
Q39: Which of the following is not a
Q40: In a PERT network, the earliest (activity)start
Q41: Table 11-1
The following represents a project with
Q42: Given an activity's optimistic, most likely, and
Q43: Given the following small project, the critical
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents