For projects that have a daily fixed cost, it is not possible to reduce the overall duration once the cost of crashing exceeds the daily fixed cost.
Correct Answer:
Verified
Q32: The activity crash cost is equal to
Q33: The activity difference is the actual duration
Q34: Given an activity's optimistic, most likely, and
Q35: Budgets are computed using only ES times.
Q36: PERT
A)assumes that we do not know ahead
Q38: Slack time in a network is the
A)amount
Q39: Which of the following is not a
Q40: In a PERT network, the earliest (activity)start
Q41: Table 11-1
The following represents a project with
Q42: Given an activity's optimistic, most likely, and