PERT
A) assumes that we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a network technique that uses three time estimates for each activity in a project.
D) is a deterministic network technique that allows for project crashing.
Correct Answer:
Verified
Q31: The expected time in PERT is
A)a weighted
Q32: The activity crash cost is equal to
Q33: The activity difference is the actual duration
Q34: Given an activity's optimistic, most likely, and
Q35: Budgets are computed using only ES times.
Q37: For projects that have a daily fixed
Q38: Slack time in a network is the
A)amount
Q39: Which of the following is not a
Q40: In a PERT network, the earliest (activity)start
Q41: Table 11-1
The following represents a project with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents