Table 12-2
The following represents a project with four activities. All times are in weeks.
-According to Table 12-2, there are four activities in the project. Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. If you wished to find the probability of finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard deviation to be used with the normal distribution. What variance would be used?
A) 2
B) 4
C) 8
D) 12
E) None of the above
Correct Answer:
Verified
Q41: Given an activity's optimistic,most likely,and pessimistic time
Q41: Table 12-1
The following represents a project with
Q42: Table 12-1
The following represents a project with
Q45: Table 12-2
The following represents a project with
Q47: Given the following small project, the critical
Q48: Table 12-1
The following represents a project with
Q50: Given an activity's optimistic,most likely,and pessimistic time
Q51: Given an activity's optimistic,most likely,and pessimistic time
Q51: Table 12-1
The following represents a project with
Q57: Given an activity's optimistic,most likely,and pessimistic time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents