If three workers are assigned to a task lasting four days, two workers are assigned a task lasting three days, and one worker is assigned to a task lasting three days.The tasks can be completed independently of each other.If you are to schedule with a resource-limit, what is the minimum resource limit for the project?
A) Three workers per day
B) 21 worker-days
C) Seven days
D) Additional information is needed to determine the minimum number.
Correct Answer:
Verified
Q35: Resource constraints are represented in the network
Q36: Resource requirements graphs based on an as-soon-as-possible
Q37: Technical constraints for a project are represented
Q38: Resource utilization charts based on each activity's
Q39: Activities in a network diagram are drawn
Q40: Which of the following is likely not
Q41: If three activities are using the same
Q42: When performing resource-limited scheduling, those activities with
Q44: If not enough resources are available for
Q45: A project is resource leveled without resource-limited
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents