If not enough resources are available for a project, to maintain the same project scope and budget, the project team should
A) accelerate the activities that have enough resources to free the needed resources.
B) delay some activities until the resource is available.
C) hire additional resources.
D) start the tasks on the day they are scheduled to start and expect unassigned resources from other activities to complete the work.
Correct Answer:
Verified
Q35: Resource constraints are represented in the network
Q36: Resource requirements graphs based on an as-soon-as-possible
Q37: Technical constraints for a project are represented
Q38: Resource utilization charts based on each activity's
Q39: Activities in a network diagram are drawn
Q40: Which of the following is likely not
Q41: If three activities are using the same
Q42: When performing resource-limited scheduling, those activities with
Q43: If three workers are assigned to a
Q45: A project is resource leveled without resource-limited
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents