Dave Is Conducting Rough-Cut Capacity Planning (RCCP)for a Product GTB

Question 11

Multiple Choice

Dave is conducting Rough-Cut Capacity Planning (RCCP) for a product GTB.The product GTB' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A and B.The Production Routings for product GTB is presented below.Using RCCR approach, find the Capacity Requirements for 4 units of product GTB.
Dave is conducting Rough-Cut Capacity Planning (RCCP) for a product GTB.The product GTB' BOM has 2 levels.The assembly is at level 1.At level 2, there are component A and B.The Production Routings for product GTB is presented below.Using RCCR approach, find the Capacity Requirements for 4 units of product GTB.   A)  WC1: 1.2 hours WC2: 3.6 hours WC3: 5.6 hours B)  WC1: 2.2 hours WC2: 3.1 hours WC3: 3.6 hours C)  WC1: 1.2 hours WC2: 3.1 hours WC3: 1.2 hours D)  WC1: 5.2 hours WC2: 1.2 hours WC3: 5.6 hours


A) WC1: 1.2 hours WC2: 3.6 hours WC3: 5.6 hours
B) WC1: 2.2 hours WC2: 3.1 hours WC3: 3.6 hours
C) WC1: 1.2 hours WC2: 3.1 hours WC3: 1.2 hours
D) WC1: 5.2 hours WC2: 1.2 hours WC3: 5.6 hours

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents