Product gamma requires a sequence of 5 Work centers.What is the capacity efficiency when the total out output is 2000 units per period? The following is the period production volume for each WC.
WC1: 2500 units, WC2: 2250 units, WC3:3100 units, WC4:2500 units, WC5:2150 units
A) 87.54%
B) 64.51%
C) 93.02%
D) 107.50%
Correct Answer:
Verified
Q10: Which of the following is a correct
Q11: Dave is conducting Rough-Cut Capacity Planning (RCCP)for
Q12: Capacity is the measure of productive capability
Q13: Capacity Requirements Planning (CRP)is a Capacity planning
Q14: AE Manufacturing has 60 machine hours every
Q16: Using RCOF and the information in
Q17: Using RCOF and the information in
Q18: The movie theater has scheduled 6 showings
Q19: Among the alternative RCCP approaches, name the
Q20: Capacity planning is the creation of a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents