Which of the following is a correct description of Capacity requirements planning (CRP) ?
A) Process of converting the master production schedule into requirements for key resources
B) Process of reconciling the difference between available capacity and load
C) Create long term capacity plans synced with business plans
D) Monitors work-center capacity imbalances
Correct Answer:
Verified
Q5: _ is a major function of the
Q6: There are 3 work stations (WC)with the
Q7: Choose the statements that differentiate the Resource
Q8: Choose, among the following examples of capacity,
Q9: Of the following solutions for overloaded work
Q11: Dave is conducting Rough-Cut Capacity Planning (RCCP)for
Q12: Capacity is the measure of productive capability
Q13: Capacity Requirements Planning (CRP)is a Capacity planning
Q14: AE Manufacturing has 60 machine hours every
Q15: Product gamma requires a sequence of 5
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents