The overall risk factor for the project is known to be 0.5. The individual failure probability and consequence scores are not known with certainty, only that all of the failure probability scores are identical and all of the consequence scores are identical. What are the individual failure probability scores?
A) 0.316
B) 0.267
C) 0.236
D) 0.347
Correct Answer:
Verified
Q26: With a maturity risk of 0.3,a complexity
Q31: A project team assesses their primary risk
Q34: A project team assigns probabilities of 0.1,0.2,and
Q36: The probability that legal and managerial structures
Q40: The mouse executive board meeting was drawing
Q46: The project team toiled long into the
Q54: The professor wore both a belt and
Q56: With a cost factor of 0.8,a schedule
Q58: What are the basic qualitative methods for
Q76: The firm set aside a little extra
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents