Which of the following statements concerning the critical path in project network is FALSE?
A) The critical path is the sequence of activities between a project's start and finish that takes the longest to finish.
B) Activities on the critical path have zero slack.
C) Delaying an activity on the critical path delays the entire project.
D) There is always only one critical path in a project network.
Correct Answer:
Verified
Q12: A project has three paths. A- B-
Q13: The earliest start time for an activity
Q14: Which one of the following best describes
Q15: If the sum of the variances on
Q16: Assuming a beta distribution is being used,
Q18: Before beginning to create a PERT/CPM network
Q19: In an activity- on- node (AON) network,
Q20: Which one of the following situations is
Q21: _ is the shortest time in which
Q22: What are the benefits of using CPM/PERT?
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents