A project has three paths. A- B- C has a length of 25 days. A- D- C has a length of 15 days. Finally, A- E- C has a length of 20 days. Which one of the following statements is TRUE?
A) A- B- C has the most slack.
B) The expected duration of this project is 25 days.
C) The expected duration of this project is 25 + 15 + 20 = 60 days.
D) A- D- C is the critical path.
Correct Answer:
Verified
Q7: Activity slack is defined as
A) earliest finish
Q8: Which one of the following statements about
Q9: In a network diagram, an "activity"
A) is
Q10: If a project has multiple critical paths,
Q11: Following are four sets of most optimistic,
Q13: The earliest start time for an activity
Q14: Which one of the following best describes
Q15: If the sum of the variances on
Q16: Assuming a beta distribution is being used,
Q17: Which of the following statements concerning the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents