In a network diagram, an "activity"
A) is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.
B) must always have a single, precise estimate for the time duration.
C) should always be something the company has had experience with.
D) is the largest unit of work effort consuming both time and resources that a project manager can Schedule and control.
Correct Answer:
Verified
Q4: Which one of the following conditions violates
Q5: Which of the following is NOT one
Q6: When using the beta probability distribution to
Q7: Activity slack is defined as
A) earliest finish
Q8: Which one of the following statements about
Q10: If a project has multiple critical paths,
Q11: Following are four sets of most optimistic,
Q12: A project has three paths. A- B-
Q13: The earliest start time for an activity
Q14: Which one of the following best describes
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents