The earliest start time for an activity is equal to the
A) smallest earliest finish time of all of its immediate predecessors.
B) largest earliest finish time of all of its immediate predecessors.
C) largest late finish time of all of its immediate predecessors.
D) smallest late start time of any of its immediate predecessors.
Correct Answer:
Verified
Q8: Which one of the following statements about
Q9: In a network diagram, an "activity"
A) is
Q10: If a project has multiple critical paths,
Q11: Following are four sets of most optimistic,
Q12: A project has three paths. A- B-
Q14: Which one of the following best describes
Q15: If the sum of the variances on
Q16: Assuming a beta distribution is being used,
Q17: Which of the following statements concerning the
Q18: Before beginning to create a PERT/CPM network
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents