Which one of the following statements about network diagrams is TRUE?
A) In an activity- on- arc diagram, the arcs depict the activities as well as the precedence relationships.
B) In an activity- on- node diagram, "events" are used to denote the end points of arcs.
C) In an activity- on- arc diagram, there is never a need to use "dummy" activities.
D) In an activity- on- node diagram, the nodes depict precedence relationships as well as activities.
Correct Answer:
Verified
Q3: In making an estimate of the most
Q4: Which one of the following conditions violates
Q5: Which of the following is NOT one
Q6: When using the beta probability distribution to
Q7: Activity slack is defined as
A) earliest finish
Q9: In a network diagram, an "activity"
A) is
Q10: If a project has multiple critical paths,
Q11: Following are four sets of most optimistic,
Q12: A project has three paths. A- B-
Q13: The earliest start time for an activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents