In making an estimate of the most pessimistic time for an activity, a manager deliberately estimates this time too high (i.e., longer than it should be) . What is the result of this action, assuming the beta distribution is being used to make time estimates?
A) The expected time for this activity will be larger than it should be.
B) The beta distribution will be symmetric around its mean.
C) The most likely time for this activity will be larger than it should be.
D) The variance of the activity will be smaller than it should be.
Correct Answer:
Verified
Q1: To calculate the probability of completing a
Q2: Assuming a beta distribution is being used,
Q4: Which one of the following conditions violates
Q5: Which of the following is NOT one
Q6: When using the beta probability distribution to
Q7: Activity slack is defined as
A) earliest finish
Q8: Which one of the following statements about
Q9: In a network diagram, an "activity"
A) is
Q10: If a project has multiple critical paths,
Q11: Following are four sets of most optimistic,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents