To calculate the probability of completing a project by a certain date,
A) the variance of the distribution of project completion times is taken to be one- sixth the difference between the latest finish time and the earliest finish time of the last activity in the project.
B) we assume that the activity durations are independent of each other so that the normal distribution can be used.
C) the expected completion time of the project is taken to be the sum of the activity times on the shortest path.
D) we only need the parameters of the beta distribution for the finish node of the diagram.
Correct Answer:
Verified
Q2: Assuming a beta distribution is being used,
Q3: In making an estimate of the most
Q4: Which one of the following conditions violates
Q5: Which of the following is NOT one
Q6: When using the beta probability distribution to
Q7: Activity slack is defined as
A) earliest finish
Q8: Which one of the following statements about
Q9: In a network diagram, an "activity"
A) is
Q10: If a project has multiple critical paths,
Q11: Following are four sets of most optimistic,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents