Solved

If a Project Has Multiple Critical Paths, Which of the Following

Question 10

Multiple Choice

If a project has multiple critical paths, which of the following variances should be used in analyzing project completion time probabilities?


A) the sum of the variances for all critical paths
B) the critical path with the smallest variance
C) the average variance of the critical paths
D) the critical path with the largest variance

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents