Which one of the following best describes the critical path of a PERT/CPM network?
A) the sequence of activities between a project's start and finish that has the maximum amount of activity slack.
B) the set of activities that has no precedence relationships.
C) the sequence of activities between a project's start and finish that takes the longest time to complete.
D) the sequence of activities that has the lowest normal activity cost.
Correct Answer:
Verified
Q9: In a network diagram, an "activity"
A) is
Q10: If a project has multiple critical paths,
Q11: Following are four sets of most optimistic,
Q12: A project has three paths. A- B-
Q13: The earliest start time for an activity
Q15: If the sum of the variances on
Q16: Assuming a beta distribution is being used,
Q17: Which of the following statements concerning the
Q18: Before beginning to create a PERT/CPM network
Q19: In an activity- on- node (AON) network,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents