Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?
A) 1, 9, 9
B) 1, 1, 9
C) 1, 5, 5
D) 1, 5, 9
Correct Answer:
Verified