Which of the following statements is INCORRECT?
A) Urgent and non-urgent changes follow the same Change Management process
B) High risk, urgent changes should be considered by the CAB Emergency Committee
C) Urgent changes need not necessarily be reviewed, unless there is time to do so
D) The justification for urgent changes should always be based on sound business reasons
Correct Answer:
Verified
Q9: Which one of the following is NOT
Q10: Which of the following is least likely
Q11: The Requirements and Strategy phase of the
Q12: The CMDB:
A) Must be available for update
Q13: Which of these statements reflect the activities
Q15: Consider the following activities: 1. The analysis
Q16: Which of the following activities are NOT
Q17: Which of these is/are TRUE? 1. Functional
Q18: The major difference between a CMDB and
Q19: During the release planning stage, you identify
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents