Which statement describes the responsibilities of a risk actionee?
A) Identifying risks to the project that might occur in their department
B) Owning and authorizing the use of the risk budget to fund risk responses
C) Managing, monitoring and controlling of all aspects of an assigned risk
D) Carrying out a risk response action to respond to a particular risk
Correct Answer:
Verified
Q63: What product identifies the management stages and
Q64: Which should be used to document any
Q65: Which is NOT included in the PRINCE2
Q66: When should the Project Board refer to
Q67: What should influence the Project Board's decision
Q69: Which is NOT a requirement of a
Q70: Which is an objective of the Closing
Q71: Which describes risk probability?
A) Level of risks
Q72: Which aspect of project performance must be
Q73: Identify the missing word(s) in the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents