What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?
A) The preference of the Project Manager
B) Having insufficient authority to perform the role
C) Having insufficient time to perform the role
D) The need to involve key stakeholders on the project management team
Correct Answer:
Verified
Q62: Which does a Project Manager produce to
Q63: What product identifies the management stages and
Q64: Which should be used to document any
Q65: Which is NOT included in the PRINCE2
Q66: When should the Project Board refer to
Q68: Which statement describes the responsibilities of a
Q69: Which is NOT a requirement of a
Q70: Which is an objective of the Closing
Q71: Which describes risk probability?
A) Level of risks
Q72: Which aspect of project performance must be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents