Which is an objective of the Closing a Project process?
A) Review and approve the plan for project closure
B) Review the performance of the project against its baseline
C) Perform any post-project reviews
D) Create a Benefits Review Plan
Correct Answer:
Verified
Q65: Which is NOT included in the PRINCE2