When should the Project Board refer to corporate or programme management for a decision?
A) The stage requires resources
B) It is forecast that project level tolerance will be exceeded
C) The Senior Supplier or Senior User needs to be changed
D) Any request for change needs to be approved
Correct Answer:
Verified
Q61: When considering how long the project stages
Q62: Which does a Project Manager produce to
Q63: What product identifies the management stages and
Q64: Which should be used to document any
Q65: Which is NOT included in the PRINCE2
Q67: What should influence the Project Board's decision
Q68: Which statement describes the responsibilities of a
Q69: Which is NOT a requirement of a
Q70: Which is an objective of the Closing
Q71: Which describes risk probability?
A) Level of risks
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents