Question 66

Multiple Choice

When should the Project Board refer to corporate or programme management for a decision?


A) The stage requires resources
B) It is forecast that project level tolerance will be exceeded
C) The Senior Supplier or Senior User needs to be changed
D) Any request for change needs to be approved