Assume you are working on a defect management process to be used by a software organization to track the current status of the defects reports for several projects. When a defect is found for investigation a defect report is created in "Opened" state that is the unique initial state. The defect report status has also a unique finale state that is the "Closed" state. The following state transition diagram describes the states of this defect management process: where only the initial ("Opened") and final ("Closed") states are indicated while the remaining states (V, W, X, Y, Z) have yet to be named. Which of the following assignments would you expect to best complete the defect management process? Number of correct responses: 1
A) V=Rejected , W=Corrected , X=Validated, Y=Re-Opened, Z=Assigned
B) V=Assigned, W=Validated , X=Corrected, Y=Re-Opened, Z=Rejected
C) V=Assigned, W=Corrected , X=Validated, Y=Re-Opened, Z=Rejected
D) V= Corrected, W=Assigned, X=Validated, Y=Corrected, Z=Rejected
Correct Answer:
Verified
Q10: You are the Test Manager of a
Q11: Assume that no additional product risks have
Q12: You are the Test Manager of a
Q13: The following chart plots the cumulative number
Q14: Which of the following statements represents the
Q16: Which of the following information would you
Q17: Which of the following is an example
Q18: Which of the following factors could negatively
Q19: Consider a defect report and assume that
Q20: Which of the following statements about the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents