You are the Test Manager of a project that adopts a V-model with four formal levels of testing: unit, integration, system and acceptance testing. On this project reviews have been conducted for each development phase prior to testing, which is to say that reviews of requirements, functional specification, high-level design, low-level design and code have been performed prior to testing. Assume that no requirements defects have been reported after the release of the product. Which TWO of the following metrics do you need in order to evaluate the requirements reviews in terms of phase containment effectiveness? Number of correct responses: 2
A) Number of defects found during the requirements review
B) Total number of defects attributable to requirements found during unit, integration, system and acceptance testing
C) Total number of defects found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing
D) Time to conduct the requirements review
E) Total number of defects attributable to requirements, found during functional specification review, high-level design review, low-level design review, code review, unit testing, integration testing, system testing and acceptance testing
Correct Answer:
Verified
Q7: The following are the requirements identified as
Q8: The following are the exit criteria described
Q9: You are following a risk-based testing strategy.
Q10: You are the Test Manager of a
Q11: Assume that no additional product risks have
Q13: The following chart plots the cumulative number
Q14: Which of the following statements represents the
Q15: Assume you are working on a defect
Q16: Which of the following information would you
Q17: Which of the following is an example
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents