You are following a risk-based testing strategy. The test execution time is very limited. Assume that all the product risk items require more or less the same level of test effort. Which of the following answers describes the best execution schedule in this scenario? Number of correct responses: 1
A) 1- Test the acceptance of transactions coming from the IVR channel 2- Test the correct charge of the Smart Card with the required contents 3- Test the correct pre-activation of the Smart Card 4- Test the correct activation of the Smart Card
B) 1- Test the correct pre-activation of the Smart Card 3- Test the correct activation of the Smart Card 4- Test the acceptance of transactions coming from the IVR channel
C) 1- Test the correct activation of the Smart Card 2- Test the correct pre-activation of the Smart Card 3- Test the correct charge of the Smart Card with the required contents
D) 2- Test the correct activation of the Smart Card
Correct Answer:
Verified
Q4: Consider an agile team adopting Extreme Programming
Q5: For which of the following activities would
Q6: After the presentation, you are asked to
Q7: The following are the requirements identified as
Q8: The following are the exit criteria described
Q10: You are the Test Manager of a
Q11: Assume that no additional product risks have
Q12: You are the Test Manager of a
Q13: The following chart plots the cumulative number
Q14: Which of the following statements represents the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents