During a Sprint Planning session, the team argues about the work estimates for a particular story. The Product Owner estimates five days. The Lead Architect estimates two days. The Scrum Master estimates eight days. The team member working on it estimates seven days. What value (in days) should be used for planning?
A) 2
B) 5
C) 7
D) 8
Correct Answer:
Verified
Q35: A team has eleven members spread over
Q36: A 200 member project team is working
Q37: What is the relationship between the Product
Q38: A story was estimated at eight ideal
Q39: A team estimates a Story using the
Q41: During a Sprint, the team completes four
Q42: A team is estimating story points. They
Q43: Suppose that you track the Sprint progress
Q44: The team determines that it has over-committed
Q45: Who is accountable for a task that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents