Suppose that you track the Sprint progress in a Burn-Down chart. You have added an extra line to show the planned progress. The line of the actual progress stays below the planning line. What does this say about the progress?
A) You are ahead of schedule.
B) You are behind schedule.
C) You have not planned well.
Correct Answer: