A team is estimating story points. They estimate that the story falls between a large (13) and a medium (5) and they assign a story point of 8. What is this technique called?
A) Affinity estimation
B) Fibonacci estimation
C) Triangulation
Correct Answer:
Verified
Q37: What is the relationship between the Product
Q38: A story was estimated at eight ideal
Q39: A team estimates a Story using the
Q40: During a Sprint Planning session, the team
Q41: During a Sprint, the team completes four
Q43: Suppose that you track the Sprint progress
Q44: The team determines that it has over-committed
Q45: Who is accountable for a task that
Q46: Which Scrum event is meant to look
Q47: Why is the "Time & means or