The team determines that it has over-committed itself for a Sprint. Who should be present when reviewing and adjusting the Sprint work?
A) The team, the Scrum Master and the Product Owner. The Stakeholders should be consulted.
B) The team and the Scrum Master. The Product Owner should be consulted.
C) The team only. The Product Owner should be consulted.
Correct Answer:
Verified
Q39: A team estimates a Story using the
Q40: During a Sprint Planning session, the team
Q41: During a Sprint, the team completes four
Q42: A team is estimating story points. They
Q43: Suppose that you track the Sprint progress
Q45: Who is accountable for a task that
Q46: Which Scrum event is meant to look
Q47: Why is the "Time & means or
Q48: Which statement describes Release Planning?
A) After looking
Q49: A team is trying to convince a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents