A project sponsor asks if a construction project can be accelerated to meet a new timeline. The project manager analyzes the schedule and finds insufficient float to accommodate the new delivery date. If more resources are provided, which of the following strategies would BEST help to achieve the new date?
A) Fast track
B) Burn
C) Crash
D) Reduce durations
Correct Answer:
Verified
Q413: In which of the following circumstances would
Q414: A project manager is overseeing the construction
Q415: A Scrum team is completing a sprint;
Q416: The vendor management team has requested all
Q417: On larger projects, a vendor may occasionally
Q419: A project manager has gathered time estimates
Q420: A highly skilled, key project team member
Q421: A team member has finalized a discussion
Q422: A company hires an outside vendor to
Q423: A project is in the initiation phase.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents