Solved

A Project Manager Has Gathered Time Estimates for a New

Question 419

Multiple Choice

A project manager has gathered time estimates for a new project's activities and is now ready to begin developing the schedule. Which of the following would the project manager most likely do NEXT?


A) Create a WBS.
B) Determine predecessors and dependencies.
C) Determine the critical path.
D) Prioritize tasks.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents