Question 421

Multiple Choice

A team member has finalized a discussion with the board of directors, but the Chief Financial Officer (CFO) is complaining about the large amount of money the project requires. Which of the following is the BEST change control process to follow?


A) Identify, implement, approve, evaluate, validate, update, communicate
B) Identify, evaluate, approve, implement, validate, update, communicate
C) Identify, approve, evaluate, implement, validate, update, communicate
D) Identify, validate, evaluate, approve, implement, update, communicate

Correct Answer: