The late finish time (LF) is ______.
A) the latest possible date an activity can be completed without delaying the project's completion
B) the maximum extent to which an activity can be delayed
C) the latest possible date an activity can be completed before the activity becomes irrelevant
D) the latest possible time an activity can be completed on a given day
Correct Answer:
Verified
Q45: The numbers in the AOA method represent
Q46: In the AOA method,_.
A)an arrow represents an
Q47: In a Gantt chart,the time to complete
Q48: Which of the following statements is true
Q49: A drawback of Gantt charts is _.
A)they
Q51: The Gantt Chart _.
A)links project activities to
Q52: Precedence diagramming is also known as _.
A)network
Q53: Which of the following statements is true
Q54: Early start time (ES)refers to _.
A)the earliest
Q55: Which of the following correctly pairs a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents