Early start time (ES) refers to ______.
A) the earliest time on a given day that the project can start/continue
B) the earliest possible date on which an activity can start based on previous activities
C) the latest time on a given day that the project can start/continue
D) the earliest possible date on in a year that an activity can start
Correct Answer:
Verified
Q49: A drawback of Gantt charts is _.
A)they
Q50: The late finish time (LF)is _.
A)the latest
Q51: The Gantt Chart _.
A)links project activities to
Q52: Precedence diagramming is also known as _.
A)network
Q53: Which of the following statements is true
Q55: Which of the following correctly pairs a
Q56: Which of the following statements is a
Q57: Which of the following statements is true
Q58: In the AON method,_.
A)the node represents the
Q59: Early finish time (EF)_.
A)is the earliest possible
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents