Which of the following statements is a correct and useful rule in constructing networks?
A) Network diagrams start at the top right and flow down to the left.
B) We can never have one arrow crossing another.
C) An activity cannot begin until all preceding activities have been completed.
D) An activity can be repeated as desired.
Correct Answer:
Verified
Q51: The Gantt Chart _.
A)links project activities to
Q52: Precedence diagramming is also known as _.
A)network
Q53: Which of the following statements is true
Q54: Early start time (ES)refers to _.
A)the earliest
Q55: Which of the following correctly pairs a
Q57: Which of the following statements is true
Q58: In the AON method,_.
A)the node represents the
Q59: Early finish time (EF)_.
A)is the earliest possible
Q60: Which of the following is a limitation
Q61: "Crashing" a project _.
A)is speeding up a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents