Which of the following correctly pairs a technique with its approach?
A) The program evaluation and review technique (PERT) uses probabilistic estimation to determine the duration of an activity.
B) The critical path method (CPM) uses subjective estimation to determine the duration of an activity.
C) The program evaluation and review technique (PERT) uses optimistic estimation to determine the duration of an activity.
D) The critical path method (CPM) uses pessimistic estimation to determine the duration of an activity.
Correct Answer:
Verified
Q50: The late finish time (LF)is _.
A)the latest
Q51: The Gantt Chart _.
A)links project activities to
Q52: Precedence diagramming is also known as _.
A)network
Q53: Which of the following statements is true
Q54: Early start time (ES)refers to _.
A)the earliest
Q56: Which of the following statements is a
Q57: Which of the following statements is true
Q58: In the AON method,_.
A)the node represents the
Q59: Early finish time (EF)_.
A)is the earliest possible
Q60: Which of the following is a limitation
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents