Which of the following statements is true with regard to the distribution of time for the duration of an activity?
A) The optimistic time estimate is 3 times shorter than the pessimistic time estimate.
B) The most likely time estimate is located at an equidistant interval between the optimistic and pessimistic estimates.
C) The pessimistic and optimistic times are asymmetrical around the mean.
D) The standard deviation for the pessimistic estimate is higher than that for the optimistic estimate.
Correct Answer:
Verified
Q48: Which of the following statements is true
Q49: A drawback of Gantt charts is _.
A)they
Q50: The late finish time (LF)is _.
A)the latest
Q51: The Gantt Chart _.
A)links project activities to
Q52: Precedence diagramming is also known as _.
A)network
Q54: Early start time (ES)refers to _.
A)the earliest
Q55: Which of the following correctly pairs a
Q56: Which of the following statements is a
Q57: Which of the following statements is true
Q58: In the AON method,_.
A)the node represents the
Unlock this Answer For Free Now!