In the AON Method,______

Question 58

Multiple Choice

In the AON method,______.


A) the node represents the path to the next project activity
B) the arrow represents the sequencing of tasks from node to node through the network
C) the arrow represents the actual time taken to complete a task in a project
D) the arrow represents the scheduled time to complete a task in a project

Correct Answer: