In the AON method,______.
A) the node represents the path to the next project activity
B) the arrow represents the sequencing of tasks from node to node through the network
C) the arrow represents the actual time taken to complete a task in a project
D) the arrow represents the scheduled time to complete a task in a project
Correct Answer:
Verified
Q53: Which of the following statements is true
Q54: Early start time (ES)refers to _.
A)the earliest
Q55: Which of the following correctly pairs a
Q56: Which of the following statements is a
Q57: Which of the following statements is true
Q59: Early finish time (EF)_.
A)is the earliest possible
Q60: Which of the following is a limitation
Q61: "Crashing" a project _.
A)is speeding up a
Q62: A critical path consists of _.
A)activities that
Q63: At a merge point,_.
A)the largest preceding EF
Unlock this Answer For Free Now!