Early finish time (EF) ______.
A) is the earliest possible date in the year on which an activity can be completed
B) is calculated by adding the duration for an activity to the ES
C) is calculated by subtracting the duration for an activity from the ES
D) is the earliest possible time on a day on which an activity can be completed
Correct Answer:
Verified
Q54: Early start time (ES)refers to _.
A)the earliest
Q55: Which of the following correctly pairs a
Q56: Which of the following statements is a
Q57: Which of the following statements is true
Q58: In the AON method,_.
A)the node represents the
Q60: Which of the following is a limitation
Q61: "Crashing" a project _.
A)is speeding up a
Q62: A critical path consists of _.
A)activities that
Q63: At a merge point,_.
A)the largest preceding EF
Q64: The backward pass _.
A)starts at the end
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents