Question 1
True/False
To use the enumeration method of determining the critical path,we list or enumerate all of the paths through the network.
Question 2
True/False
The critical path is the sequence of schedule activities determining the duration of the project,and is generally the shortest path through the project.
Question 3
True/False
The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish" (FF).
Question 4
True/False
When developing a project schedule,total float refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project end date.
Question 5
True/False
The length of time to perform an activity is often dependent upon who will do that work.
Question 6
True/False
The "start-to-start" logical relationship used in activity sequencing applies to the case in which a successor activity cannot start until a predecessor activity has started.
Question 7
True/False
A mandatory dependency is a logical relationship between activities that must happen - usually due to a physical or legal demand.
Question 8
True/False
There is often terrific pressure to complete a project as quickly as possible.To confront this pressure,a project manager should quickly promise to meet the deadlines requested by the sponsor and then assemble a team to create the corresponding schedule.
Question 9
True/False
In the enumeration method the project schedule is calculated many times (perhaps 1,000 or more),and each time,the estimate for a particular activity is generated based on the likelihood of that time as determined by the project manager.