Use this scenario for the following questions.
The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
-Refer to the scenario above.How many workers must be added to increase the output rate to one unit per minute?
A) 1
B) 2
C) 3
D) 4
Correct Answer:
Verified
Q62: Use this scenario for the following
Q63: Use this scenario for the following
Q71: The table depicts an production line that
Q72: Use this scenario for the following
Q72: The process design team at a manufacturer
Q79: Use this scenario for the following
Q84: Use this scenario for the following
Q90: The maximum allowable time between completions of
Q94: Use this scenario for the following
Q97: Consider any collection of tasks to be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents