The Overall Project Risk Factor Is Known to Be 0

Question 57

Multiple Choice

The overall project risk factor is known to be 0.6.The probability of dependency failure is twice the probability of complexity failure and four times the probability of maturity failure.The consequence of performance failure is twice the consequence of reliability failure,four times the consequence of schedule failure and eight times the consequence of cost failure.What is the probability of maturity failure?  Maturity X Cost Y Complexity 2X Bchedule  2Y  Dependency 4X Reliability  4Y  Performance  8Y \begin{array} { | l | l | l | l | } \hline \text { Maturity } & \mathbf { X } & \text { Cost } & \mathbf { Y } \\\hline \text { Complexity } & \mathbf { 2 X } & \text { Bchedule } & \text { 2Y } \\\hline \text { Dependency } & 4 \mathrm { X } & \text { Reliability } & \text { 4Y } \\\hline & & \text { Performance } & \text { 8Y } \\\hline\end{array}


A) 0.213
B) 0.197
C) 0.104
D) 0.148

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents