The overall project risk factor is known to be 0.6.The probability of dependency failure is twice the probability of complexity failure and four times the probability of maturity failure.The consequence of performance failure is twice the consequence of reliability failure,four times the consequence of schedule failure and eight times the consequence of cost failure.What is the probability of maturity failure?
A) 0.213
B) 0.197
C) 0.104
D) 0.148
Correct Answer:
Verified
Q52: The overall project risk factor is
Q53: The pointy-haired dean gently suggested that study
Q54: The professor wore both a belt and
Q55: The overall risk factor for the
Q56: With a cost factor of 0.8,a schedule
Q58: What are the basic qualitative methods for
Q59: When new projects involve unproven technology,they are
Q60: Garman yawned as he sat at his
Q61: The task contingency reserves address higher-level risks.
Q62: The budget safety measures that address higher
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents