Once most of the design work is complete,at a point when the scope and capabilities of the project are quite well understood,a ________ may be developed.
A) definitive estimate
B) comparative estimate
C) parametric estimate
D) non-parametric estimate
Correct Answer:
Verified
Q29: Effective comparative estimates rely most heavily on:
A)An
Q30: An order of magnitude estimate is usually
Q31: Which of these estimates should be the
Q32: If a project manager is using a
Q33: Cost estimates that are based as a
Q35: When their baby was ready to head
Q36: Analogous estimation is a type of _
Q37: The analogous estimation method is a bottom-up
Q38: An activity with a learning rate of
Q39: If it takes 40 hours to complete