Here are the data for a time-cost CPM scheduling model analysis.The time is in days and the costs include both direct and indirect costs.
What are the total time of this project and total normal cost?
A) Total time is 13 days, total cost is $1,200.
B) Total time is 12 days, total cost is $1,700.
C) Total time is 11 days, total cost is $1,600.
D) Total time is 10 days, total cost is $1,750.
E) Total time is 9 days, total cost is $1,700.
Correct Answer:
Verified
Q59: A simple project listing of five activities,
Q60: You have just been assigned to oversee
Q61: Here are the data for a time-cost
Q62: You have collected the data for a
Q63: In CPM analysis, it is generally expected
Q65: You have just used the network planning
Q66: You have collected the data for a
Q67: You have just performed a CPM analysis
Q68: You know when you have arrived at
Q69: You have just used the network planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents