You have just used the network planning model and found the critical path length is 60 days and there are two critical paths.The standard deviation of the first critical path is 10 days and the s.d.of the second critical path is 15 days.The probability that the project will be completed in 70 days or less is equal to (2 decimal accuracy)
A) 0.84
B) B.0.25.
C) 0.16
D) 0.75
E) 0.66.
Correct Answer:
Verified
Q62: You have collected the data for a
Q63: In CPM analysis, it is generally expected
Q64: Here are the data for a time-cost
Q65: You have just used the network planning
Q66: You have collected the data for a
Q67: You have just performed a CPM analysis
Q68: You know when you have arrived at
Q70: Popular project management software used in mid-sized
Q71: You have the following time and cost
Q72: You have just used the network planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents