You Have Just Used the Network Planning Model for a County

Question 72

Multiple Choice

You have just used the network planning model for a county road resurfacing project and found the critical path length is 40 days and the standard deviation of the critical path is 10 days.Suppose you want to pick a time (in days) within which you will complete the project with 90% confidence level, what should be that time (in days and round to the nearest whole number.)


A) 40
B) B.13.
C) 37
D) 29
E) 53